Posted on: August 1, 2018

UPDATE REGARDING STREET REPLACEMENT PROJECT IN BRENTWOOD PARK AND HASLET PARK


NOTE: Due to soil conditions discovered during construction in Brentwood Park, the methodology of compaction was changed & specifications adjusted for the remainder of Brentwood Park and for Haslet Park to eliminate vibratory rolling on the project by the contractor, except as may be required by site conditions to meet the compaction requirements.

*The full depth reclamation of Brentwood Park is complete.
*The next phase is concrete placement and compaction of the concrete.
*Access may be cutoff to your property for up to 6 hours while the concrete cures.
*The full removal and stabilization of the streets is expected to begin on or around:
8/1 Odessa; 8/6 Berry; and 8/9 Schreiber
*The roller compacted concrete placement on the streets is expected to begin on or around:
8/6 Brentwood-All Streets
8/9 Odessa; 8/14 Berry; and 8/20 Schreiber
*Please note that the dates and order are subject to change.

For a complete update on the Brentwood Park & Haslet Park Street Replacement Project see the brochure online at www.Haslet.org/DocumentCenter/View/1913

Contact City Engineer Travis Attanasio at 817-439-5931 or the project contractor DDM Construction at 940-726-1121 with questions or concerns.